Action plan for CBS Migration in Kerala Circle


Directorate vide e-mail dated 17.01.2014, it is intimated that the CBS will be implemented in the Circle on 10th March 2014.  A checklist for activities related to the migration to the CBS platform has been prepared by DMCC Tamil Nadu and published in SDC Website.


Vendors of Infosys, the FSI will be visiting the Post Offices to undertake the digitization of the manual data (Prior to computerisation including the discontinued schemes, Savings Certificate details etc).  The documents relating to the manual data has to be segregated and kept ready for the data entry.  Necessary support to the vendor to digitize the manual records should be extended by the Post Offices.  Also the data entry should be verified and authenticated by the Supervisor on data-to-day basis. This is because this digitized data will be updated in the CBS-Finacle software where chances are very remote for further data correction.  Also care should be taken that all the manual data is got captured digitally without any omissions.

Time line for the Pilot Offices in Kerala Circle

         Kottarakara HO, Punalur HO, Neyyattinkara HO on 10.03.2014

Sl No
Activity
Scheduled Date
1
Opening of POSB accounts for credit of Commission by the Agents and linking in Sanchaya Post
31.01.2014
2
Installation of latest version of Sanchaya Post, DBA and DPT
31.01.2014
3
Settlement of DBA/DPT discrepancies
03.02.2014
4
Receiving nominations for User Champion and End User Trainings
03.02.2014
5
Selection of IT Support Team in the Region/Division
03.02.2014
6
Meeting Software requirements  (Finacle and OS Windows 7)
20.02.2014
7
Meeting Network requirements
20.02.2014
8
Meeting Hardware requirements
20.02.2014
9
Digitization of manual data
25.02.2014
10
User Champion training
25.02.2014
11
End User Training
25.02.2014
12
Training for IT Team
25.02.2014
13
Training for MPKBY Agents/SAS Agents
25.02.2014
14
Mock migration
01.03.2014
15
Migration
10.03.2014*





                                                                                                              

 * Date of migration for the HOs under Calicut Division are given below:
          Calicut HO – 17.03.14
          Calicut CS HO – 24.03.14
          Kalpetta HO-31.03.14

Time line for non-piloted offices
Sl No
Activity
Scheduled date
1
Opening of POSB accounts for credit of Commission by the Agents and linking in Sanchaya Post
31.01.2014
2
Installation of latest version of Sanchaya Post, DBA and DPT
31.01.2014
3
Settlement of DBA/DPT discrepancies
03.02.2014
4
Receiving nominations for User Champion and End User Trainings
10.02.2014
5
Selection of IT Support Team in the Region/Division
10.02.2014
6
Meeting  Software requirements                              (Finacle and OS Windows 7)
25.02.2014
7
Meeting Network requirements
25.02.2014
8
Meeting Hardware requirements
01.03.2014
9
Digitization of manual data
01.03.2014
10
User Champion training
01.03.2014
11
End User Training
01.03.2014
12
Training for IT Team of the Region/Division
01.03.2014
13
Training for MPKBY Agents/SAS Agents
01.03.2014
14
Mock migration
20.03.2014
15
Migration
31.03.2014